    Study on Installation of Neutral Ground Resistance in Very Small Power Plant Transformer
    (2022-01-01)
    Chiradeja, Pathomthat
    ;
    ;
    Srisuksai, Panu
    ;
    ;
    Faults in the distribution system of the Thai electrical system occur frequently. Such faults directly affect the protective equipment of the distribution system. The protective device disconnects the circuit unnecessarily on many occasions because it detects a higher current than expected. In this study, a 22-kV distribution system and a very small power plant (VSPP) were connected. The system consists of two feeders. Feeder 1 supplies electricity directly to the load; a fault was enforced in this feeder. Feeder 2 supplies electricity directly to the load; the VSPP was connected to this feeder. The fault in Feeder 1 was simulated, and the behavior of the defense system was studied. Unnecessary disconnection of the VSPP circuit took place because the high fault current caused the overcurrent protection relay to operate instantaneously. Therefore, a neutral ground resistance was installed at the VSPP transformer to reduce the fault current, extend the relay operating time to the delay range, and reduce unnecessary disconnections of the overcurrent protection relay of the VSPP. In addition, when a fault occurs in the distribution system, the faulted phase voltage decreases, whereas the non-faulted phase voltage increases. Surge arresters and voltage transformers must be able to withstand an increase in voltage. This is also explained and discussed in this paper.
  • Some of the metrics are blocked by your 
    Item type:Publication,
    An Approach for Voltage Drop Improvement in Distribution Line Using High-Voltage Capacitor Bank
    (2025-01-01)
    Songsukthawan, Panapong
    ;
    ;
    Thongsuk, Surakit
    ;
    Phannil, Natthanon
    ;
    Bunjongjit, Sulee
    Distribution line voltage drops cause power losses and a general decline in the efficiency of the electrical power system. In this study, PSCAD software is used to evaluate the elements that impact the voltage drop in the distribution line, including distribution line length, electric load power factor, and electric load capacity, both with and without capacitor bank installation. The 22-kV overhead distribution line in Thailand served as the basis for the simulation model’s creation. It has been suggested to install capacitor bank-based techniques to increase voltage on distribution lines. The findings show that the voltage drop is significantly influenced by the distribution line distance, electric load power factor, and electric load capacity. The voltage drop can be minimized to the greatest extent by properly arranging capacitor banks.
  • Some of the metrics are blocked by your 
    Item type:Publication,
    Very Small Power Plant Transformer Without and With Installation of Neutral Ground Resistance on Relay Operation
    (2024-01-01) ;
    Chiradeja, Pathomthat
    ;
    ;
    Srisuksai, Panu
    ;
    In this study, a double-feeder 22 kV distribution system connected to a very small power plant (VSPP) was simulated in the PowerFactory DIgSILENT program. A neutral ground resistance (NGR) was introduced to reduce a ground fault current from the VSPP, extend the relay operating time to the delay range, and reduce undesired trip of non-faulty feeder that VSPP connected. Thus, the overcurrent protection relay was simulated to analyze working patterns during faults. Three types of VSPP transformer NGR installations were considered: VSPP without NGR, VSPP with a Bisection method approach, and VSPP with the proposed symmetrical component calculation approach. Moreover, this study analyzed the effect of overvoltage on the distribution system with the proposed systematic component calculation approach under fault conditions. The result from the case study indicated that the NGR installation with the proposed approach can reduce the fault current and shift delay time of the protection device to avoid maloperation.
  • Some of the metrics are blocked by your 
    Item type:Publication,
    Downtime Reduction with Fast Restart Function in a Beverage Production System
    (2023-01-01) ;
    Phannil, Natthanon
    ;
    ;
    Thongsuk, Surakit
    ;
    Bunjongjit, Sulee
    Bottled-beverage production systems require considerable machinery and sophisticated control systems. A malfunction in the production system can result in machine stoppages, thereby decreasing productivity and resulting in the production output not meeting the required target. Therefore, the problem of frequent stoppages of the production system must be resolved. The ‘Fast Restart Function’ is a proposed feature that can help reduce machine downtime by decreasing the time required for the product to drain from the conveyor. In this study, using this strategy, the investigated manufacturing system’s efficiency increased from 86.81% to 90.29%, enabling an increase in the average production capacity by 27,187 bottles per day, i.e., a 3.48 percent increment of the daily capacity. When employed in inefficient production systems or systems facing frequent shutdowns, this system is of considerable value for mitigating production stoppages.